How do I know a Dubai renovation contractor is legitimate, and how should I pay them so I do not end up with half a project and no money?
Check three things before you transfer money to a Dubai renovation contractor: that the company holds a valid trade licence whose activity list covers the work you are buying, that it is registered with Dubai Municipality as a contractor, and that it can file the permit in its own name, because Dubai law requires a Municipality-approved contractor or a pre-qualified consultant to submit the application and an owner cannot file it. Then pay against completed and inspected stages written into the contract, never against dates, and hold retention until the defects period ends. DLA Piper's construction bulletin of 8 October 2025 makes the reason plain: the UAE has no construction payment statute, no statutory adjudication and no requirement that your money be ring-fenced, so nothing protects you except what the contract says.
The checks to do before you transfer anything
The disputes that end up on UAE legal forums often start the same way. A large sum paid against a one-page quotation, to a company the owner never verified, with a security cheque in hand that turned out to be worth less than it looked. The checks below take an afternoon. They are the difference between a contractor you can pursue and a phone number that stops answering.
- Get the legal name and the licence numberNot the trading name on the social media account. Ask for a copy of the trade licence and the registered address, and read the licence properly rather than glancing at it.
- Check the licence through a government channelThe UAE government's own portal lists the channels for checking a business licence: the economic department of the relevant emirate, and the federal National Economic Register at growth.gov.ae, which covers all seven emirates. For a Dubai licence it points to two lookups, Dubai Economy and Tourism's e-services search and the Invest in Dubai platform. A Dubai mainland business needs a trade licence from the Department of Economy and Tourism (DET), the authority formerly known as the Department of Economic Development.
- Read the activity list, not just the statusDubai Municipality categorises contracting and engineering-consultancy activities separately and sets binding standards for each. A valid licence is not proof that the firm is licensed for the work you are buying, so check that the activity you need is actually on it.
- Ask for the Dubai Municipality registrationA trade licence is not the only credential. Dubai Municipality maintains its own Consultants and Contractors Register, which is a separate registration from the DET licence, and says its approved consultants, contractors and suppliers data can be checked through its own system. Ask for the registration and check it there.
- Ask who will submit the permit, and in whose nameThis is the fastest test of the lot. Administrative Resolution No. (85) of 2019 requires an application for a decoration works permit to be submitted by a contractor approved by Dubai Municipality, and Administrative Resolution No. (109) of 2022 requires a consulting engineer or contractor pre-qualified by the Municipality to file maintenance works through the Dubai Building Permit System. The owner is not a submitting party. If the company cannot file in its own name, it is not approved, whatever the brochure says.
- Ask for the insurance certificates and read the datesWe could not find a Dubai authority that publishes a required insurance schedule for residential fit-out, so treat cover as a contract term rather than an assumption. Name the policies you want in the contract, ask for the certificates, and check the expiry dates and the sums insured yourself.
- Take up two references, and ask them about moneyNot whether they were happy. Ask how variations were priced once work had started, how long the final account took to settle, and whether the snag list was closed after the final payment was made.
What you can actually verify, and what nobody publishes
Verification in Dubai is layered. Different bodies hold different parts of the picture and none of them holds all of it, so it helps to know what each check does and does not prove.
| Document | Who issues it | Where it can be checked | What it does not tell you |
|---|---|---|---|
| Trade licence | Dubai's Department of Economy and Tourism (DET), formerly the Department of Economic Development | The UAE government portal points to DET's e-services search and the Invest in Dubai platform | Whether the licence covers the specific work being sold to you |
| Economic register entry | The federal National Economic Register at growth.gov.ae | Listed on u.ae, which lets you look up a licence, an activity or a trade name across all seven emirates | Anything at all about how the firm performs on site |
| Contractor registration | Dubai Municipality, through its Consultants and Contractors Register | Dubai Municipality states that its approved consultants, contractors and suppliers data can be checked through its own system | Classification detail, which the Municipality does not publish in the form the blogs describe |
| Ability to file a permit | Dubai Municipality, through approval of the contractor or pre-qualification of the consultant | Ask the firm to name the permit it will file, and the system it will file it in | Whether the firm has the capacity to start when it says it will |
What Law No. (7) of 2025 changed, and what it does not do for you
Dubai issued Law No. (7) of 2025 regulating contracting activities in the emirate, announced by the Dubai Media Office on 12 July 2025. Kennedys records that it was published on 8 July 2025 and came into force on 8 January 2026, with contractors already operating given until 8 January 2027 to bring themselves into line. The Media Office release describes contracting activity running through a single Dubai Municipality system covering registration, classification and oversight, reaching every contractor in Dubai including those in special development zones and free zones such as the DIFC, with airport-related contracting carved out.
Penalties under the law run from AED 1,000 to AED 100,000 according to the same release, and a repeat breach within a year can double that to a maximum of AED 200,000. Al Tamimi & Company reports that Dubai Municipality and the supervising authorities can inspect sites, decide complaints made against contractors and impose penalties.
Two limits matter to you as a client. The compliance window runs to January 2027, so a firm's absence from the new register does not yet prove much on its own. And nothing published says that a prospective client can search that register: it is a regulator's instrument first. The same caution applies to Dubai Municipality's updated Contractor and Engineering Consultancy Rating System, reported by Gulf News on 29 June 2025 as coming into force by 2026, with owners and developers feeding into it through surveys on the Build in Dubai platform. Whether the resulting scores can be looked up by someone choosing a firm is not something the Municipality has stated publicly.
The contract is the only thing protecting your money
DLA Piper's construction bulletin of 8 October 2025 states the point most Dubai advice skips. The UAE has no construction payment statute of the kind found in the UK or Australia, no statutory adjudication, and no legal requirement that your money be ring-fenced. What protects you is what the contract says, and a one-page quotation says almost nothing.
A contract worth signing has attachments. If these are not in the envelope, you are agreeing to a price for an idea.
- The drawing set, listed by number and revision, so both sides know which version was priced
- A bill of quantities with rates, not a lump sum, so a variation can be priced against something
- A programme with dates, and what happens to them if you are late giving a decision
- The variation procedure: who prices extra work, on what rates, and who signs it off before it is built
- Payment stages tied to inspected milestones rather than calendar dates
- Retention and the defects liability period, in figures and in days
- Who applies for the permit, in whose name, and who pays the authority fees
- Named products and finishes, with what happens if a specified item cannot be sourced
- The snagging and handover process, and what counts as completion
- Which parts of the work will be subcontracted, and to whom
One protection does come from the law rather than the contract. Under the UAE Civil Code, a contractor and the supervising engineer are jointly and severally liable for ten years from handover if the building collapses in whole or in part, or if a defect appears that threatens its stability and safety. Squire Patton Boggs records that the Civil Code was replaced in full by Federal Decree-Law No. 25 of 2025, in force since 1 June 2026, and Charles Russell Speechlys, writing on 18 May 2026, places that liability at Articles 821 to 824. Contracts entered into before 1 June 2026 are generally still governed by the old code.
How to stage the payments so you stay in control
There is no standard deposit set by law or by any authority in Dubai, and no published figure worth trusting. Every percentage that circulates for Dubai residential fit-out, the thirty to forty per cent deposit and the milestone splits that go with it, traces back to interior-design and contractor marketing sites writing to justify their own terms. There is no government source and no law-firm source for any of them.
What you can insist on is that money only ever moves against something that exists. An advance should be tied to a signed scope, a dated programme and security for the sum paid ahead. After that, every payment follows an inspection.
| Stage | What must exist before you release the money | What this protects you from |
|---|---|---|
| Advance on signing | A signed contract with the drawings, bill of quantities and programme attached, and security for the advance | Paying for a project that has not yet been defined |
| Mobilisation and procurement | The permit applied for in the contractor's name, the site formally handed over, and orders placed for long-lead items with copies sent to you | Money leaving before anything has been ordered |
| First fix complete | A joint walk of the works, with services closed up only after you have seen them open | Paying for work you will never be able to inspect again |
| Finishes and second fix | Delivered materials matching the specification in the bill of quantities, checked on site rather than on a delivery note | Quiet substitution of the specified products |
| Practical completion and handover | A snag list issued, agreed and closed, and the completion documents in your hands | Paying in full against an open snag list |
| End of the defects liability period | The retention released only once the period has run | Defects surfacing after the contractor has been paid everything |
On retention, the practice is well attested but it is not a rule. DLA Piper (October 2025) and an article in Chambers of 24 July 2024 both describe a common position of 10 per cent of the contract value, with 5 per cent released at handover and 5 per cent after the defects liability period, and both describe twelve months from completion as the usual defects period. Read that as practice on construction contracts generally rather than as a published benchmark for a villa fit-out. Retention is not mandated by UAE statute, so if it is not written into your contract you do not have it. A claim you may meet online that Federal Law No. 2 of 2014 caps retention at 5 per cent should be ignored: no such law exists.
The security cheque is not the protection you think it is
A security cheque, sometimes called a guarantee cheque, is commonly exchanged on construction work in the UAE, typically to secure an advance payment or performance under the contract. KH Legal, writing on 21 May 2026, confirms the practice and names construction expressly.
The law underneath it has moved. Federal Decree-Law No. 14 of 2020 amended the Commercial Transactions Law with effect from 2 January 2022 and repealed Articles 401 to 403 of the Penal Code, as BSA Law set out in November 2021; the rules now sit in Federal Decree-Law No. 50 of 2022. A cheque that bounces purely for insufficient funds is no longer a criminal matter, it is a debt you enforce. Chambers, on 11 June 2026, explains the other half: a returned cheque is itself a writ of execution under Article 667, so the holder can go straight to the execution judge instead of first winning a civil case. Bad faith remains criminal under Article 675, which covers ordering the bank not to pay, closing or emptying the account, or signing a cheque so that it cannot be paid, as does forgery under Article 676.
So the cheque is faster than it used to be and weaker than it sounds. KH Legal notes that UAE courts have held an enforceable cheque is not the same as a judgment: it is rebuttable evidence, and the person who wrote it can resist enforcement by showing it was only ever security and that nothing is presently due. Take the cheque if it is offered. Do not treat it as money in the bank, and never let it stand in for a payment schedule that keeps you close to the work.
If the money has already gone
The routes people are usually pointed to are mostly the wrong ones, and knowing which is which saves weeks.
| Route | What it can do | What it cannot do |
|---|---|---|
| Dubai Economy and Tourism consumer rights | Handles consumer complaints of other kinds | Gulf News, reporting on the process on 6 April 2025, lists construction and contracting among the matters DET does not accept, alongside real estate, banking and fraud |
| Rental Disputes Centre | Decides disputes between landlords and tenants, and jointly owned property disputes | Hear a dispute with your contractor, which is not a landlord and tenant relationship |
| Dubai Municipality, call centre 800 900 | Takes complaints around the clock, and is the place to raise a contractor breaching building rules on site; the Municipality has issued warnings to engineering consultancy offices and suspended firms | Recover your money. A regulator penalising a contractor is not the same as being repaid |
| Dubai Courts | Decide a claim for breach of contract and award what is owed | Start before any pre-action step that applies to your claim has been dealt with |
| Police | Act where there is fraud or breach of trust, money taken with no intention of performing or funds diverted from your project | Deal with ordinary non-performance, which is civil. Take legal advice before filing anything criminal |
One practical point on the court route. Smaller claims may have to pass through the Centre for Amicable Settlement of Disputes before a court will register them. BSA Law, writing on 20 June 2025, places civil claims below AED 500,000 within the Centre's jurisdiction under Decision No. 4 of 2025, while other firms reading the same decision describe the Centre's role more narrowly. The readings differ, so take advice on your specific claim rather than assuming either version applies to you.
Handyman, fit-out contractor or design-and-build studio
The legal line here is clearer than the marketing one. Administrative Resolution No. (85) of 2019 provides that decoration works in a unit larger than 100 square metres cannot start without a Dubai Municipality permit. Units of 100 square metres or less, and units inside a trade centre, are exempt from the permit, but the work must still be done by a contractor approved by the Municipality. That leaves an unapproved handyman with a much narrower slice of work than most owners assume.
A fit-out contractor prices and builds drawings someone else produced, which works well when those drawings are complete and badly when they are not. A design-and-build studio carries both sides, so the drawing and the price cannot quietly stop agreeing with each other. HST works that way across interior design and renovation and fit-out: the team that draws the project also builds it. Two completed examples are the gym renovation in Al Wasl and the Springfield office fit-out in Business Bay.
Which permit your job needs depends on where the property sits, and that is a separate question covered in our guide to which authority approves your renovation. If you would like a second opinion on a quotation or a draft contract before you sign it, send us the documents and we will tell you what is missing from them.
Sources
Figures and rules on this page come from the sources below. Where a number is ours, it says so. Rules and fees in Dubai change; the date beside each source is when we read it.
- u.ae, Verify business licences Updated 6 April 2026
- u.ae, National Economic Register Updated 17 April 2026
- Dubai Department of Economy and Tourism, Licences and Permits Accessed 20 September 2026
- Dubai Municipality, Consultants and Contractors Licensing Standards Page last modified 19 September 2026
- Dubai Municipality, Consultants, Contractors and Suppliers Data Accessed 20 September 2026
- Dubai Municipality, Frequently Asked Questions (call centre 800 900) Accessed 20 September 2026
- Dubai Media Office, Mohammed bin Rashid issues law regulating contracting activities in Dubai 12 July 2025
- Kennedys, Dubai Law No. 7 of 2025: A new era for the construction sector July 2025
- Al Tamimi & Company, A New Era for Contractors in Dubai 2026
- Dubai Media Office, Dubai Municipality issues warnings to engineering consultancy offices 26 August 2025
- Gulf News, Dubai to launch new contractor rating system by 2026, suspends two firms 29 June 2025
- Dubai Legislation Portal, Administrative Resolution No. (85) of 2019 Concerning the Licensing of Decoration Works 17 March 2019
- Dubai Legislation Portal, Administrative Resolution No. (109) of 2022 Regulating the Licensing of Maintenance Works 20 April 2022
- DLA Piper, Global Construction Bulletin, Security of payment: UAE 8 October 2025
- Chambers and Partners, Retentions in UAE Construction Contracts: A Comparative Analysis 24 July 2024
- Squire Patton Boggs, Client Update on the New Civil Law in the UAE: Federal Decree Law No. 25 of 2025 January 2026
- Charles Russell Speechlys, Decennial Liability and Subcontractors under the New UAE Civil Code: Articles 821 to 824 18 May 2026
- KH Legal, Guarantee Cheques in UAE: Can They Still Be Challenged? 21 May 2026
- Chambers and Partners, Cheque Bounce and Debt Recovery in the UAE 11 June 2026
- BSA Law, Latest amendments in relation to bounced cheques in the UAE 19 November 2021
- Gulf News, How to file a consumer complaint in Dubai 6 April 2025
- Rental Disputes Centre, About RDC Site last updated 18 June 2026
- BSA Law, Dubai Expands Jurisdiction of the Centre for Amicable Settlement of Disputes 20 June 2025
Questions we are asked next

Before you sign anything A second opinion on the paperwork
Send us the quotation, the drawings and the draft contract and we will tell you what is missing before any money moves. Office 1603, Burj Khalifa, Downtown Dubai. Saturday to Thursday, 9am to 6pm.