Which authority approves your Dubai renovation, and in what order
How do I know whether Dubai Municipality, Trakhees or DDA handles my renovation, and do I need a developer NOC as well?
Which authority handles your renovation depends on who supervises the land, not on what you are building. Law No. (16) of 2023 gives Dubai Municipality the power to issue planning permits across the emirate and gives the authorities supervising free zones and special development zones the same power over the land they supervise, so a mainland villa goes to Dubai Municipality, a unit in the TECOM districts to the Dubai Development Authority, and Nakheel and PCFC land to Trakhees. You need the master developer's or building owner's No Objection Certificate before the authority application, because the authority asks for it as a submission document, and the application must be filed by a registered consultant or contractor, not by you.
Who issues the permit where you are
The useful question is not what kind of work you are doing. It is who supervises the ground the building stands on. Law No. (16) of 2023 on urban planning, published on the Dubai Legislation Portal, gives Dubai Municipality authority to issue all types of planning permits, and gives the authorities supervising special development zones and free zones the same authority over the land under their supervision.
The standard behind those doors is shared. Law No. (3) of 2026 on the quality and safety of buildings, issued on 27 February 2026, applies to every building in the emirate including free zones such as the DIFC, and calls all of these bodies Competent Entities. The Dubai Building Code, given legal force by Decree No. (45) of 2021, applies emirate-wide too.
| Where the property is | Who issues the permit | What the authority's own source says |
|---|---|---|
| Mainland Dubai, including freehold villa communities and towers outside a free zone | Dubai Municipality, through its Buildings Regulation and Permits Agency, on the Build in Dubai portal (formerly branded Dubai BPS) | Law No. (16) of 2023 gives Dubai Municipality all types of planning permits; dm.gov.ae places building permits with the Buildings Regulation and Permits Agency |
| The TECOM districts: Dubai Internet City, Media City, Studio City, Production City, Knowledge Park, International Academic City, Science Park, Design District, Outsource City, Industrial City, in5, DQuarters | Dubai Development Authority (DDA) | DDA's own page names these twelve districts as the ones it regulates |
| Land owned by PCFC, Dubai World and their subsidiaries, which includes Nakheel's developments and Dubai Maritime City | Trakhees, the regulatory arm of the Ports, Customs and Free Zone Corporation | PCFC names Nakheel, Limitless and Dubai Maritime City. Palm Jumeirah and JAFZA follow from that ownership rather than being listed by name |
| Jumeirah Lakes Towers | DMCC issues an NOC addressed to Concordia, the community's facilities manager, which approves the fit-out | DMCC Application Guideline 2.1.2, requested through the DMCC member portal |
| Dubai Airport Free Zone, Dubai Silicon Oasis, Dubai CommerCity | Dubai Integrated Economic Zones Authority (DIEZ) licenses and regulates the three zones, but its permit route is not published | Law No. (16) of 2021 established DIEZ over these three zones. No published permit procedure was found for it, so ask the zone directly |
| Dubai South | Not published | dubaisouth.ae publishes nothing about building permits or a submission portal. Any procedure quoted for it online is unsourced |
Two traps. Business Bay is not on the Dubai Development Authority's published list, so do not assume DDA covers it because Dubai Design District is nearby; Business Bay work such as the Springfield Office fit-out is not a DDA job. And Trakhees information no longer sits on trakhees.ae, which redirects to pcfc.ae. Where a community is not on an authority's own list, the title deed and the master developer's correspondence settle it.
Does this job need a permit at all
For decoration work, Dubai Municipality draws the line at floor area. Administrative Resolution No. (85) of 2019 says decoration works in a unit larger than 100 square metres cannot start without a Municipality permit, and its Article 4 exempts a unit of any size inside a trade centre, and a unit of 100 square metres or less, from both the permit and the completion certificate. Even exempt work must still be carried out by a contractor approved by the Municipality.
Gulf News reported the same threshold in May 2023 and listed the covered works as suspended ceilings, flooring, shelving and internal partitions. One naming point: what the trade calls Circular 231 of 2018 carries no such number on Dubai Municipality's circulars index, last modified 19 September 2026. The live document is circular 3-8-1, Self-Permit for Interior Decoration Works, dated 23 August 2021.
Structural work sits under an older rule. Article 4 of Local Order No. (3) of 1999 bars construction works that permanently or temporarily change the features of land or property without a permit from the competent department, which covers extensions, pools and moving walls. In a tower, the apartment renovation guide covers what the building's own rules add.
The developer NOC comes first, and it is not the permit
A developer NOC and an authority permit are two things, and you need both in that order. The Dubai Development Authority's fit-out permit page lists an NOC from the building owner, and NOCs from the relevant authorities, among the documents the contractor submits with the application. Documents submitted with an application necessarily precede it. DMCC shows the same pattern from the other side: its Application Guideline 2.1.2 has the company or property owner request an NOC addressed to Concordia through the member portal. DMCC publishes no fee and no turnaround for it.
Names have moved, which matters when hunting for the right form. nakheelcommunities.com now redirects to Dubai Holding Community Management, which manages Nakheel, Meraas and Dubai Properties communities after the Nakheel and Meydan merger under Dubai Holding. For Emaar, be careful with numbers: the Emaar Community Management home modifications page could not be retrieved when checked on 20 September 2026, and the NOC fees, deposits and area charges circulating online are not published by Emaar or Nakheel. Get the figure from your community team in writing.
The order of submission
- Establish who supervises the landCheck the title deed and master developer against the lists above. Getting this wrong costs weeks, because the drawing set is prepared for the authority you submit to.
- Get the site plan or property mapThe Dubai Land Department charges AED 225 for the unified land map issued with Dubai Municipality and AED 250 for a villa or apartment map, plus AED 10 knowledge and AED 10 innovation fees per drawing, in a stated 12 minutes. In DDA districts the site plan is AED 1,000 and two working days, and the plot owner may request it.
- Get the master developer or landlord NOCIt belongs inside the permit application, not alongside it. For a tenant, the landlord's NOC and the Ejari copy both sit here.
- Appoint the consultant and contractorThey are the applicant, not you. The owner's part is to sign the appointment letter, which DDA lists as a submission document.
- Submit on the right portalBuild in Dubai for Dubai Municipality, DDA's own permit services for the TECOM districts, Trakhees through PCFC, the DMCC member portal for the JLT NOC.
- Deal with Civil Defence only if the job triggers itDubai Civil Defence runs engineering drawing approvals through its Smart Services platform. When that is triggered is set out below.
- Build, inspect and close the permit outIn DDA districts a Dubai Civil Defence completion certificate is required before the fit-out completion certificate can be issued.
You cannot file the application yourself
Administrative Resolution No. (85) of 2019 requires a decoration works permit application to be submitted by a contractor approved by Dubai Municipality. Administrative Resolution No. (109) of 2022 requires maintenance works permits to come from a consulting engineer or contractor pre-qualified by the Municipality, through the Dubai Building Permit System. Dubai Municipality's villa permit procedure, version 4 dated 10 May 2020, assigns the permit request to the consultant; the owner appears nowhere as a responsible party. Every DDA permit card names the requester as the contractor.
There is one contrary text, and people quote it. Article 3 of Local Order No. (3) of 1999 defines the applicant as an owner or his legal representative. It is from 1999, and the later resolutions and the portals require a registered professional to file, so the owner appoints and signs while the consultant or contractor submits. Law No. (3) of 2026 points the same way, requiring the owner's application to name the engineering firm.
That is the practical reason a design-and-build practice handles its own submissions: the team that drew the scheme can file it and amend it without a handover in the middle. If you want to work out who would submit on your job, tell us where the property is.
What actually goes in the submission
The Dubai Development Authority publishes its fit-out set plainly: the request form, a contractor appointment letter signed by the tenant, a copy of the Ejari, an NOC from the building owner, NOCs from the relevant authorities, and the approved stamped drawings alongside the proposed ones. Note what is not there. No affection plan line, and no separate MEP or fire drawing items, both of which the blogs add.
The pairing of stamped approved drawings with proposed ones is the part people underestimate. The authority compares your proposal against what was permitted, so a scheme drawn from a site measure, without the stamped set it modifies, has nothing to be compared against. Dubai Municipality publishes no equivalent checklist, and its villa procedure dates from May 2020, which is part of why the blogs fill the gap with invented lists.
What the authorities publish as fees
Government fees are a small part of a renovation budget and rarely the number people are quoted. Below are the figures the authorities publish themselves. Anything above them in an approvals package is a service charge.
| Item | Authority | Published fee | Stated time |
|---|---|---|---|
| Fit-out permit | Dubai Development Authority | AED 0.90 per square foot, minimum AED 200, maximum AED 10,000, plus AED 10 knowledge and AED 10 innovation dirhams | 2 working days |
| Building modification permit | Dubai Development Authority | AED 1.00 per square foot, plus the same two AED 10 fees. Renewal AED 200 | 2 working days |
| Final building permit | Dubai Development Authority | AED 1.00 per square foot of total built-up area, minimum AED 200, capped at AED 250,000 on industrial plots | 2 working days |
| Construction works permit, private residential building | Dubai Municipality, Local Order No. (3) of 1999, Schedule 2 | AED 0.30 per square foot, with no minimum stated | Not published |
| Alterations to villas, private houses and annexes | Dubai Municipality, Local Order No. (3) of 1999, Schedule 6 | AED 200 application fee | Not published |
| Engineering audit of villa plans and minor alterations | Dubai Municipality, Local Order No. (3) of 1999, Schedule 1 | AED 100 initial application, first re-submission free, AED 100 from the second re-submission | Not published |
Two caveats. The Municipality figures come from Local Order No. (3) of 1999, which is 26 years old. It is still operative, proved by Executive Council Resolution No. 65 of 2022 amending its schedules item by item on 9 November 2022, but confirm the rate before relying on it. And DDA's two working days is its processing time once a complete application lands, not the elapsed time from your first drawing. The villa renovation cost guide covers the rest of the budget.
When Civil Defence is actually involved
Dubai Civil Defence approval is not automatic on every fit-out. Dubai Municipality's own permit procedure states that the task for Dubai Civil Defence is generated if required only, using that formula for adjustments, additions and decoration work as for new buildings. In DDA districts Civil Defence sits at the closing gate instead: a Dubai Civil Defence completion certificate is required before the fit-out completion certificate, and DDA's modification and final building permit pages mention it nowhere.
One correction on the code. Dubai Civil Defence still publishes the September 2018 edition of the UAE Fire and Life Safety Code of Practice as the operative code, on a page last updated 11 June 2026. There is no 2025 or 2026 edition, so a claim that your job must meet new fire rules issued this year is unsupported.
What gets applications sent back
Most rejections are administrative and follow from the requirements above. The NOC is missing, or addressed to the wrong party: in JLT the DMCC NOC goes to Concordia, not to the contractor. The applicant is wrong, because an owner has tried to file what the law reserves to a pre-qualified consultant or contractor. The proposed drawings arrive without the stamped approved set they modify. Or the file went to the wrong authority, which happens most on PCFC and Dubai World land, where people assume Dubai Municipality.
Timing quietly kills permits too. Under Local Order No. (3) of 1999 a construction works permit may be cancelled if works have not started within three months of issue, or have been suspended on site for more than three consecutive months; Schedule 4 sets renewal at 10 per cent of the issuance fee for a further six months. DDA charges AED 200 to renew a building modification permit. If a job stalls between design and site, the permit clock keeps running.
Starting before the permit is a different problem. Article 4 of Local Order No. (3) of 1999 bars the works outright, Article 20 requires the engineer to suspend work immediately if the contractor commits a violation, and the consequences are in our guide to work done without a permit. Whether the job is an extension or an interior scheme, the cheapest week is the one spent establishing the route before anyone draws.
Sources
Figures and rules on this page come from the sources below. Where a number is ours, it says so. Rules and fees in Dubai change; the date beside each source is when we read it.
- Dubai Legislation Portal, Law No. (16) of 2023 Concerning Urban Planning in the Emirate of Dubai 7 July 2023
- Dubai Legislation Portal, Law No. (3) of 2026 Concerning the Quality and Safety of Buildings 27 February 2026
- Dubai Legislation Portal, Decree No. (45) of 2021 Concerning the Dubai Building Code 18 November 2021
- Dubai Legislation Portal, Local Order No. (3) of 1999 Regulating Construction Works in the Emirate of Dubai (Articles 4, 3, 9, 20, 26, 28 and Schedules 1, 2, 4, 6, 7) 15 November 1999, schedules amended 9 November 2022
- Dubai Legislation Portal, Administrative Resolution No. (85) of 2019 Concerning the Licensing of Decoration Works 17 March 2019
- Dubai Legislation Portal, Administrative Resolution No. (109) of 2022 Regulating the Licensing of Maintenance Works 20 April 2022
- Dubai Legislation Portal, Law No. (16) of 2021 Establishing the Dubai Integrated Economic Zones Authority 2021
- Dubai Municipality, Buildings Regulation and Permits Agency Page last modified 19 September 2026
- Dubai Municipality, Building & Planning Circulars (circular 3-8-1, Self-Permit for Interior Decoration Works, dated 23 August 2021) Page last modified 19 September 2026
- Dubai Municipality, Procedure of Issuing Building Permit & Building Completion Certificate from DM (Villas) Version 4, 10 May 2020
- Build in Dubai (Dubai Municipality permit platform; dubaibps.dm.gov.ae redirects here) Observed 20 September 2026
- Dubai Government Media Office, Dubai Municipality launches Building in Dubai platform 18 October 2023
- Dubai Development Authority, Fit-Out Permit service card Retrieved 20 September 2026 (page undated)
- Dubai Development Authority, Building Modification Permit service card Retrieved 20 September 2026 (page undated)
- Dubai Development Authority, Final Building Permit service card Retrieved 20 September 2026 (page undated)
- Dubai Development Authority, Site Plan Issuance Retrieved 20 September 2026 (page undated)
- Dubai Development Authority, TECOM Group districts Checked 20 September 2026 (page undated)
- Ports, Customs and Free Zone Corporation, About Trakhees (trakhees.ae now redirects to pcfc.ae) Page last updated 1 January 2026
- DMCC, Application Guideline 2.1.2, Request for NOC to Concordia, Fit-Out Retrieved 20 September 2026 (document undated, version 2.1.2)
- Dubai Land Department, Property Map Request Site last updated 8 September 2026
- Dubai Civil Defence, UAE Fire and Life Safety Code of Practice (September 2018 edition) Page last updated 11 June 2026
- The General Command of Dubai Civil Defence, Smart Services Page last updated 11 June 2026
- Dubai Holding Community Management (nakheelcommunities.com redirects here) Retrieved 20 September 2026
- Emaar Community Management, home modifications FAQ (returned HTTP 403 and could not be read) Checked 20 September 2026
- Dubai South (no building permit or fit-out procedure published) Retrieved 20 September 2026
- Dubai Media Office, Hamdan bin Mohammed amends various legislations (Executive Council Resolution No. 65 of 2022) 9 November 2022
- Gulf News, Want to change home decor in Dubai? You may need this permit from Dubai Municipality 31 May 2023
- Gulf News, Small shops in Dubai exempted from decoration works licence 15 December 2018
Questions we are asked next

Tell us the address We will work out which authority it goes to
HST Architects is a design-and-build studio working on interior design, renovation and fit-out, and landscaping across Dubai. Send us the location and the scope and we will set out the route, the NOC and the submission before anyone starts drawing.